Heavy Industrial Plant Cooling Loop Modernization
Modernization of a 4,500 m³/h open recirculating cooling tower experiencing severe scaling, high blowdown losses, and manual biocide dosing.
The Core Engineering Challenge:
The client experienced frequent heat exchanger tube pluggage every 4 months due to airborne sand ingestion and uncontrolled cycles of concentration. Make-up water consumption was surging, and biological slime was insulating condenser bundles.
The Baseline / Existing System:
Manual timer blowdown valve, erratic drum chemical pumping, no side-stream filtration, basin accumulated 15 cm of sand annually.
What C-Water Engineered:
Technology Stack Deployed:
Measured Performance Improvements:
Virtually doubled water re-use efficiency within the cooling loop.
Significant reduction in facility raw water acquisition and treatment bills.
Zero emergency plant downtime caused by condenser scaling.
Working Through a Similar Water Challenge?
Speak with a C-Water senior engineer to discuss your facility requirements and design a tailored solution.